Questions? Complaints? Concerns?

Current Construction Projects


Location of Work: On 3 Mile Road between M-84 and Midland Road, in Bay County’s Frankenlust Township.

UPDATE AS OF 10/18/24: 3 Mile Road construction completion is scheduled in the next three weeks.  We apologize that there have been multiple delays on this complex project outside of our and the contractor’s control, but the project is nearing completion.  We appreciate your patience and understanding!   Final update: The final layer of asphalt has been placed, and asphalt driveways will be completed today.   We plan to begin gravel shoulders placement on Monday, followed by yard final topsoiling and grading and gravel driveway placement, which will take the remainder of next week.   The week of October 28th, the manholes in the HMA will be adjusted, concrete will be poured around them, and they will need to cure (approximately 5 days); dormant seeding will then be placed, permanent signs will be placed, and pavement striping will be placed.  The Project is scheduled to be completed in the first week of November. Just so you know, this is weather-dependent, which can affect these dates, but this is our current schedule.  

Impact on Traffic:  Road closed to through traffic, local traffic permitted.


Location of Work: On Midland Road between US-10 and Carter Road, in Bay County’s Williams Township – NOW COMPLETE!


Location of Work:

  1. Parish Road from Fraser Road to M-13 – COMPLETE
  2. Freeland Road from Mackinaw Road to M-84 – COMPLETE
  3. Pine Road from Cass Avenue to Youngs Ditch Road – COMPLETE
  4. Munger Road from Pine Road to M-15 – COMPLETE
  5. Midland Road from the Auburn City Limits to 7 Mile Road

Estimated Work Duration/Schedule:

  1. (1 week), July 29, 2024 to August 2, 2024
  2. (3 days), August 19,2024 to August 21, 2024
  3. (3 days), September 3, 2024 to September 5, 2024
  4. (3 days), September 30, 2024 to October 4, 2024
  5. (2 weeks) October 14, 2024 to October 28, 2024

Description of Work: The existing pavement will be milled and resurfaced and shoulders reconstructed.

Impact on Traffic:  Roads will remain open with lane closures and flaggers.


Location of Work: On 7 Mile Road from Linwood Road to Erickson Road, in Bay County’s Fraser
Township.

Estimated Work Duration/Schedule: (3 months), August 19, 2024 – November 15, 2024

Description of Work: 3.93 miles of drainage improvements, HMA base crushing and shaping, HMA
paving, shoulders, and permanent pavement markings.

Impact on Traffic: Road closed to through traffic with signed detour route, local traffic permitted.